Project is targeted to take 4 months. This is an arbitrary amount set by internal leadership, but will serve as a useful data point in our guidance document.
Eventually we'll have something more Useful, but here are some important dates for how the project will run.
- Tool Selection
- Design - 6/20/2012
- Sencha Test - 6/21- 7/6/2012
- jQuery/PhoneGap Test - 7/9 - 7/13/2012
- MonoTouch Test - 7/16 - 7/20/2012
- Appcelerator Test - 7/23 - 7/27/2012
- Final Selection - 7/30 - 8/3/2012
- Visual Prototypes
- Initial Set Ready- 6/25 - 8/3/2012
- Additional Prototypes - Ongoing
- Functional Prototyping
- Ongoing Development
- Initial Iteration- 8/6 - 8/28/2012
- Iteration #2 - 8/29 - 9/18/2012
- Iteration #3 - 9/19 - 10/9/2012
- Iteration #4 - 10/10 - 10/30/2012
- Iteration #5 - 10/31 - 11/20/2012
- Beta
- Internal Beta (EIS) 10/12 - 10/26/2012
- App Submission
- iTunes - 12/16/2012
- Play - 12/16/2012
- Guidance Report
- Initial Draft - 12/16/2012
Please note that this is not a comprehensive timeline. There are many additional tasks and things going on. If you'd like to add them, please do.
Scheduled vacation:
Sara - 9/3-9/17
Brian - 9/26 - 10/5